Gonçalves-Dosantos, J.C.García-Jurado, IgnacioCosta, Julián2024-01-312024-01-312020Gonçalves-Dosantos, J.C., García-Jurado, I. & Costa, J. Sharing delay costs in stochastic scheduling problems with delays. 4OR-Q J Oper Res 18, 457–476 (2020). https://doi.org/10.1007/s10288-019-00427-91619-45001614-2411http://hdl.handle.net/2183/35294This version of the article has been accepted for publication, after peer review and is subject to Springer Nature’s AM terms of use, but is not the Version of Record and does not reflect post-acceptance improvements, or any corrections. The Version of Record is available online at: https://doi.org/10.1007/s10288-019-00427-9.[Abstract]: An important problem in project management is determining ways to distribute amongst activities the costs that are incurred when a project is delayed because some activities end later than expected. In this study, we address this problem in stochastic projects, where the durations of activities are unknown but their corresponding probability distributions are known. We propose and characterise an allocation rule based on the Shapley value, illustrate its behaviour by using examples, and analyse features of its calculation for large problems.engTodos os dereitos reservados. All rights reserved.Project managementSchedulingStochastic durationsDelay costCooperative game theoryShapley valueSharing delay costs in stochastic scheduling problems with delaysjournal articleopen access10.1007/s10288-019-00427-9