Initial Impact and Socioeconomic Compensation for the Closure of a Coal-Fired Power Plant in a Local Entity
| UDC.coleccion | Investigación | es_ES |
| UDC.departamento | Empresa | es_ES |
| UDC.endPage | 17 | es_ES |
| UDC.grupoInv | Investigación en Marketing Aplicado (iMARKA) | es_ES |
| UDC.issue | 13 | es_ES |
| UDC.journalTitle | Sustainibility | es_ES |
| UDC.startPage | 1 | es_ES |
| UDC.volume | 13 | es_ES |
| dc.contributor.author | Prado-Domínguez, Antonio Javier | |
| dc.contributor.author | González-Laxe, Fernando | |
| dc.contributor.author | Escourido-Calvo, Manuel | |
| dc.contributor.author | Martín Bermúdez, Federico | |
| dc.date.accessioned | 2021-08-09T08:06:09Z | |
| dc.date.available | 2021-08-09T08:06:09Z | |
| dc.date.issued | 2021 | |
| dc.description.abstract | [Abstract] This work contributes to improving the relevant information for the local participatory process, in a context of just energy transition. A proposal has been prepared for an objective estimate of the initial impact and the minimum socioeconomic compensation for the closure of a conventional coal-fired thermal power plant in the affected local entity. This has allowed (1) specifying and contextualizing the effects into which the initial impact of the closure can be divided, with the inclusion of the circular effect; (2) obtaining an indicator of the minimum compensation that would need to be set to neutralize this impact; and (3) establishing recommendations and conclusions based on the evidence obtained. | es_ES |
| dc.description.sponsorship | This research was funded by MITECO Ministry (Government of Spain) and the As Pontes City Council.: 2019/C004/000030 | es_ES |
| dc.description.sponsorship | Concello das Pontes de García Rodríguez; 2019/C004/000030 | |
| dc.identifier.citation | Prado-Domínguez, Antonio J., Fernando González-Laxe, Manuel Escourido-Calvo, and Federico Martín-Bermúdez (2021). Initial Impact and Socioeconomic Compensation for the Closure of a Coal-Fired Power Plant in a Local Entity. Sustainability, 13, (13). https://doi.org/10.3390/su13137391 | es_ES |
| dc.identifier.issn | 2071-1050 | |
| dc.identifier.uri | http://hdl.handle.net/2183/28253 | |
| dc.language.iso | eng | es_ES |
| dc.publisher | MDPI | es_ES |
| dc.relation.uri | https://doi.org/10.3390/su13137391 | es_ES |
| dc.rights | Atribución 4.0 Internacional (CC BY 4.0) | es_ES |
| dc.rights.accessRights | open access | es_ES |
| dc.rights.uri | https://creativecommons.org/licenses/by/4.0/ | * |
| dc.subject | Coal power plant closure | es_ES |
| dc.subject | Just energy transition | es_ES |
| dc.subject | Participatory process | es_ES |
| dc.subject | Initial impact | es_ES |
| dc.subject | Local compensation | es_ES |
| dc.subject | Multilevel informational outlook | es_ES |
| dc.title | Initial Impact and Socioeconomic Compensation for the Closure of a Coal-Fired Power Plant in a Local Entity | es_ES |
| dc.type | journal article | es_ES |
| dspace.entity.type | Publication | |
| relation.isAuthorOfPublication | 50c86726-e163-4913-89e9-f3305f72023c | |
| relation.isAuthorOfPublication | 88d462f1-2561-49e8-b467-25c5e16e6752 | |
| relation.isAuthorOfPublication | 2a754b06-bd82-42bd-9bc6-9be4d7717583 | |
| relation.isAuthorOfPublication | 240098d8-85e9-4ca7-babe-4e2c6018d7dc | |
| relation.isAuthorOfPublication.latestForDiscovery | 50c86726-e163-4913-89e9-f3305f72023c |
Files
Original bundle
1 - 1 of 1
Loading...
- Name:
- sustainability-13-07391-v2.pdf
- Size:
- 553.77 KB
- Format:
- Adobe Portable Document Format
- Description: